Stage 1

February 2020

Launch of NZ Hydrogen Limited by Matthew Greaves

Stage 1

Stage 1

March 2020

Setup of main operations and lab for research and development in Northland, New Zealand.

Stage 1

Stage 1

May 2020

Launch of research and development for prototype 1 of the HMAX200 series.

Stage 1

Stage 1

December 2020

Completion of research and development for prototype 1 of the HMAX200 series.

Stage 1

Stage 2

January 2021

Launch of research and development for prototype 2 of the HMAX200 series.

Stage 2

Stage 2

November 2021

Completion of research and development for prototype 2 of the HMAX200 series.

Stage 2

Stage 3

March 2022

Launch of research and development for prototype 3 of the HMAX200 series.

Stage 3

Stage 3

October 2022

Completion of research and development for prototype 3 of the HMAX200 series.

Stage 3

Stage 4

October 2022

Starting now to raise capital funding to proceed with development with split cell hydrogen unit “HMAX200”.

Stage 4

Invest In The Future Of Hydrogen Energy